PSC approves Mon Power generation projects and financing surcharge
The companies estimate an initial residential bill increase of about $1.18 a month; the reviewed announcement gives no billing start date.

Clarksburg-area Mon Power customers have a new utility-cost development to watch: state regulators approved a financing surcharge alongside new gas and solar generation projects November 17.
The Public Service Commission said Monongahela Power and Potomac Edison estimate the initial surcharge will add approximately $1.18 per month, or 0.9 percent, to residential bills. It would recover financing costs during construction and after the facilities enter service until those costs enter base rates.
The approval covers a proposed $2.48 billion, 1,200-megawatt natural gas plant at Fort Martin in Monongalia County and 70 megawatts of solar capacity at three other sites.
The companies must provide construction and cost updates in January 2027 filings and give at least 30 days' notice before construction begins. The announcement does not establish a billing start date or completed construction.
Sources & further reading
West Virginia Public Service Commission, November 17, 2026 announcement ↗MetroNews, November 17, 2026 ↗Connect Bridgeport, Mon Power notice confirming Clarksburg service area, August 28, 2026 ↗See something that needs a correction?
Include the article title and the specific information we should check.
Continue the Conversation
Have something to say about this story? Join the discussion in our Clarksburg News and Observer Facebook community.
Visit Our Facebook GroupCommunity comments are participants’ views and are not verified Observer reporting.